Project Phases & Schedule

Phase I of this study has recommended the preferred alignment and improvements for the Polk-Quincy Viaduct. Phase I began in April 2009 and was completed in August 2011.

Phase II, the review of the "Future Design Consideration" and design of construction plans, began in early 2012 and is scheduled to be finished in 2016.

At this time, no funding for right of way acquisition or construction has been identified and a schedule for construction of the improvements has not been determined.

Current Schedule 2012 2013 2014 2015 2016
  Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Preliminary Engineering & Design                                        
Right-of-Way Appraisal Process
  currently unfunded                          
Right-of-Way Acquisition
  currently unfunded                          
Utility Adjustments   currently unfunded                          
Final Engineering and Design                                        
Construction   currently unfunded                          